Compute where the green power already is.

We put compact data centers at the substations of wind and solar parks. They run on the park's own power, including the power the grid can't take, and give companies secure computing that stays in Germany.

Green power. Distributed data centers. Sovereign data.
9.4 TWh
of renewable power curtailed in Germany in 2025 because the grid couldn't take it
64 GPUs
in one GridPark cabinet, about 56 kW, at the park's substation
100%
of your data processed in Germany, encrypted end to end
0
models trained on customer data. We don't store it either
the idea // 2:37

Where does your company's AI actually run?

In two and a half minutes: why companies' computing ends up abroad, why wind and solar parks switch off green power, and how GreenScatter connects the two.

the problem // two sides, one mismatch

Compute sits in the wrong place.

Companies need more computing every month and send it abroad. Meanwhile parks switch off green power because the grid is full. Both problems have the same fix.

01 // companies

Compute demand grows. Engineering knowledge leaves the country.

Simulation models, design data, source code and the questions engineers ask an AI are a company's most valuable assets. In the cloud they sit in foreign data centers under foreign law. In defence and automotive, that means some work can't go to the cloud at all.

+96%
worldwide spend on AI cloud infrastructure in 2026, to $42 billion
Gartner
42% → 69%
German companies using AI from the cloud
Bitkom Cloud Report 2026
85%
of German companies feel too dependent on US cloud providers
Bitkom 2026
CLOUD Act
US providers can't shield data stored in Europe from US authorities
heise, French Senate hearing, June 2025
02 // energy

Green power goes to waste. Data centers wait for new grid connections.

Wind and solar parks regularly produce more than the grid can take, and in negative-price hours they earn nothing. Big data centers need new grid connections, land and water, and face growing local resistance.

3.5%
of renewable generation curtailed in 2025
SMARD / Bundesnetzagentur
573 h
of negative power prices in 2025, about 16% of solar output
SMARD, pv magazine
≈ €3.1 bn
cost of managing grid congestion
Bundestag hib 689/2026
$198 bn
of US data center projects blocked or delayed in the first half of 2026
Data Center Watch
how it works // three parts

A data center the size of a shipping container, at the substation.

A 100 MW data center doesn't fit in a park. A 56 kW cabinet does. Our orchestration layer runs many of these small sites as one network.

wind + solar park substation fenced · monitored grid + fibre to the grid GridPark 8 servers · 64 GPUs park power Orchestration energy · data · deadline more parks ··· Your team API · portal · CLI ⚿
one day // a hybrid park, 24 hours // drag the hour

Watch a cabinet follow the park's power.

Live AI requests run when customers need them. Batch work like simulations and renderings waits for the hours when the park has power to spare. Energy then costs the park nothing extra and the cabinet the least.

Illustrative curves. Energy prices from the GreenScatter model v17: about 2 ct/kWh in surplus hours, 6 ct from the park, 12 ct from the park battery, plus electricity tax.
time
13:00
power source
Surplus park power
energy cost for the cabinet
≈ 2 ct/kWh
what's running
AI requests + batch simulations
who wins // engineering firms · park owners · germany

Every side gets something it can't get today.

engineering firms

Secure compute at a fair price, data stays in Germany.

Pay only for what you use, without buying hardware. Your team keeps its tools: an API for AI requests, a portal or command line for batch jobs, and an isolated workspace for your own software and licences.

GreenScatter€100
Market average≈ €112
Google Cloud≈ €155
AWS London≈ €248
40 GPU-hours, Nov 2026. AI tokens: €0.25 per million (IONOS ≈ €0.31, Scaleway ≈ €0.35).
park owners

A buyer on site for your power, even at negative prices.

Invest in a cabinet the way you invest in a battery. We install it, run it and bring the customers. The two work together: the battery stores the midday surplus and powers the cabinet at night.

65%
of customer revenue goes to the hardware owner. We keep 35% for operations and sales.
≈ 2.8 years
payback per 64-GPU cabinet in our base case (65% utilisation)
germany

Wasted energy used, existing grid reused.

Each cabinet uses the substation, grid connection and fibre that are already there. Money and engineering knowledge stay in the country, and rural parks earn from urban demand.

≈ 430 MWh
consumed locally per cabinet each year, with no new grid connection
why distributed // built to be questioned

Small sites, many of them, run as one network.

energy

The energy is already spread out.

Germany's renewable capacity sits in thousands of parks.

the longer story

A substation has room for a 50–200 kW cabinet. It has no room for a 100 MW data center. So instead of pulling power across the grid to one point, we bring the compute to where the power is made.

grid

No waiting for a new connection.

The cabinet uses the park's existing grid connection.

the longer story

Large data centers wait years for a new grid connection, and that has become a bottleneck. A cabinet can be installed within months, and the next one follows when demand grows.

speed

Grow in small steps.

Each step is about €1.9 million, not hundreds of millions.

the longer story

A 64-GPU cabinet costs about €1.88 million including servers. Capacity grows cabinet by cabinet, and only after customer demand is confirmed.

resilience

No single point of failure.

If one site goes down, jobs move to another park.

the longer story

Batch jobs are checkpointed and continue at another site when one stops or its energy drops. The design target is equivalent to Uptime Tier III, with the park battery, a UPS and redundant cooling as backup.

region

Compute in your region.

Jobs run near the customer, and data stays in Germany.

the longer story

Sensitive jobs are only placed on cabinets that meet their data class, for example a TISAX-compliant cabinet for confidential automotive data.

a clear limit

Hyperscalers cool more efficiently.

Google reached a PUE of 1.09 in 2025. Our free-air cooled cabinet targets about 1.25 and uses no water. Our advantage is the source of the energy, not the cooling.

security // physical · technical · certified

Your jobs arrive encrypted. Results go back. Nothing is stored.

01
Locked siteSubstations are critical infrastructure: fenced, access-controlled and monitored around the clock. The cabinet is locked, filmed and every access is logged.
02
Encrypted end to endHardware-based confidential computing keeps data encrypted in memory while it is processed. Signed, locked software only.
03
Check before you runRemote attestation lets you verify the hardware and software yourself before your job starts.
04
No access for the park ownerThe park owner has no access to your data. We don't store it and we never use it to train models. Pen tests start in the pilot.

Certification roadmap

  1. first year
    ISO 27001 readinessInformation security management from month one, audit-ready by month nine. GDPR, NIS2 and KRITIS physical protection built in.
  2. stage 2
    BSI C5 and TISAXC5 for public-sector customers, TISAX with a separate locked area for automotive prototype data.
  3. stage 3
    VS-NfD for defenceBSI-approved products and security-cleared staff. Unclassified defence work starts on ISO 27001.
alternatives // where we sit

Compute alone solves half the problem.

Providers that only sell compute build ever bigger central sites. The few that combine compute with green power work outside Germany or on open sites without access control.

global gpu cloud

AWS · Google Cloud · Azure

German regions available.

differenceUS companies under the CLOUD Act; 40 GPU-hours ≈ €155–248.
rented servers, germany

Hetzner

GPU servers in German data centers, ≈ €1,199 per month.

differenceFixed monthly rent at central sites; no hourly or token-based use.
european gpu cloud

Mistral Compute

Rented GPUs in its own data centers in France and Sweden.

differenceCentral sites, multi-year commitments, no data center in Germany.
sovereign mega data centers

Polarise · Schwarz Digits

New large data centers in Germany.

differenceNew buildings, land and cooling; years to build.
compute in wind turbines

windCORES

Rack space in turbine towers since 2018.

differenceLimited space, own parks only. We use standard containers at many owners' substations.
hpc at renewable sites

CloudGrid Energy

HPC units at parks and charging sites across Europe.

differenceNo access control at public sites; we use only locked, logged substations.
renewable gpu cloud

Verda

100% renewable GPU cloud in Finland and Iceland.

differenceCentral and outside Germany; data doesn't stay here.
home compute nodes

XFRA · Sunrun

Distributed compute nodes in homes.

differenceUSA only, not built on renewable surplus.
micro data centers at parks

GreenScatter

At the substations of wind and solar parks in Germany.

differencePark's own energy, pay per use, data stays in Germany.
hover or focus to pause
next 12 months // ingolstadt region first

From two clouds to the first cabinet.

months 1–3

Orchestration layer

First version on rented GPUs at two cloud providers, with an open-source AI model.

jobs fail over from cloud 1 to cloud 2
months 4–6

Pilot node at a substation

A single-GPU node in a locked cabinet at a park, running with the clouds as one network.

first pilot users, real usage data
months 7–9

Measure and harden

Uptime, physical and cyber security, pen testing, ISO 27001 pre-audit.

≥ 1 energy and ≥ 1 engineering pilot partner
months 10–12

First 64-GPU cabinet

Technical design, site and investment agreement with a park owner, company founding.

≥ 3 customer LOIs, financing secured
≈ 13,400
people in the Ingolstadt region who need compute: automotive, aerospace, defence, research
≈ 33 cabinets
of regional demand at 40 GPU-hours per user per month
≈ 78 cabinets
of room at regional wind and solar parks (≈ 298 MW)
team // aerospace, ai, security

Our team

Engineers from aerospace and defence. We know from the inside how sensitive data has to be protected. Supported by the THI incubator programme in Ingolstadt.

Mevlüde Tigre

Mevlüde Tigre

co-founder · product & platform
  • Software developer at Airbus Defence and Space since 2022. Previously test engineer at Turkish Aerospace Industries.
  • M.Sc. Robotics & Autonomous Systems, Universität zu Lübeck
F. Faruk Okumus

F. Faruk Okumus

co-founder · ai & research
  • AI PhD researcher at Technische Hochschule Ingolstadt. Previously flight control software engineer at Turkish Aerospace Industries.
  • M.Sc. Robotics & Autonomous Systems, Universität zu Lübeck
get in touch // pilot partners wanted

Join the pilot in the Ingolstadt region.

you need compute

Engineering firm or tech company

Tell us what you run today (AI inference, FEM/CFD, rendering) and where your data is allowed to go. We'll show you what a pilot looks like.

Email usteam@greenscatter.com
you have green power

Wind or solar park owner

We'll look at your substation, your curtailed hours and your battery plans, and calculate what a cabinet would earn at your site.

Email usteam@greenscatter.com

Our pitch deck is available on request by email.